ISO 22301 (BCMS) Lead Implementer Quiz Questions and Answers

Answer :
  • The lack of staff awareness

Explanation :

The staff of RDK attended trainings that presumably enhanced their set of skills necessary for task completion. Nonetheless, they were not trained nor made aware of potential risks that the company can be subject to, such as cyberattacks. Similarly, the lack of awareness is a reason why they were unable to undertake any action during or after the incident, given that their roles and responsibilities were not defined.
Answer :
  • Due to the necessity of minimizing the negative impacts of any operational interruption

Explanation :

Business continuity management derives from the Information Technology Disaster Recovery (ITDR), which addressed the issue of losing critical data since companies started using computers for their everyday work. Currently, business continuity management is regarded as a discipline that significantly reduces the magnitude of negative impacts deriving from business disruptions.
Answer :
  • Business impact analysis

Explanation :

The organization shall use the process for analyzing business impacts to determine business continuity priorities and requirements. The process shall identify the activities that support the provision of products and services and determine which resources are needed to support prioritized activities.
Answer :
  • Business impact analysis; recovery strategies; plan development; tests and exercises

Explanation :

To ensure the successful implementation of the BCMS, an organization should have a process for business continuity planning. This process consists of the following steps: conducting business impact analysis, identifying recovery strategies, developing a plan, and conducting tests and exercises.
Answer :
  • Determining the approach and data collection method

Explanation :

The initial activity that should be undertaken when planning the BIA is determining the approach and data collection method. The insights generated from the data collection process, then, serve to identify key products and services, select the impacts to be analyzed, and prepare the BIA tools
Answer :
  • ISO standards are developed as a response to a formal request from industry sectors or stakeholders

Explanation :

ISO develops standards for which a market demand exists, as a response to formal requests from industry sectors or stakeholders (e.g., consumer groups). ISO standards are based on global expert opinion. ISO standards are developed through a multi-stakeholder process.
Answer :
  • To implement an integrated management system

Explanation :

As organizations manage several compliance frameworks simultaneously, it is recommended to implement an integrated management system (IMS). Among others, an IMS enables an organization to reduce costs and duplications when ensuring conformity to multiple frameworks.
Answer :
  • Because business processes may expose the organization to numerous business continuity risks

Explanation :

The different business processes within an organization may pose substantially different risks to the business continuity. Therefore, the business continuity manager should assess and understand these processes in order to determine the risks that may pot
Answer :
  • TRUE

Explanation :

Interested parties are important actors in the implementation of the BCMS. The organization should ensure that all relevant interested parties are informed on the actions undertaken to ensure business continuity, as well as on their roles and responsibili
Answer :
  • Yes, as changing the scope could invalidate any certification which is reliant upon the terms of the scope statement

Explanation :

The organization should pay special attention when changing the scope, since a change to it may invalidate the certification. It is common for the scope to change over time to allow the BCMS to adapt to changing circumstances in the organization. On the o