Projects are a fundamental part of every business organisation. As a project manager, you function as an integrator who brings together all the different teams and silos working to complete the project.
According to the Project Management Institute (PMI), every project is guided by three main guardrails - schedule or time frame, scope of work, and budget. Project management professionals need to manage these three constraints effectively while ensuring the best outcome. For this, you need to monitor the status of the project ensuring maximum possible adherence to the three constraints.
Earned value refers to the value assigned to work performed within the scope, schedule and budget of your project. Depending on the nature of this work, it can be quantified in monetary terms, hours or medium of execution. This is what makes Earned Value Analysis (EVA) so important for organisations and project managers. EVA is a technique used by project managers to monitor and control the outcome of the project.
There are many benefits of EVA that you can see as your project progresses.
In 1966, when the US Air Force mandated earned value along with other planning and control requirements of Air Force programs, earned value management (EVM) became a fundamental approach to project management. Back then, it was known as Cost/ Schedule Planning Control Specification (C/ SPCS). Today about half a century later, the name has changed to EVM, but the purpose and concept of earned value remain the same.
Earned Value Management is an overarching concept that encapsulates 32 guidelines that define the requirements a management system must meet by the end of the project.
The main goals of earned value analysis are:
To apply EVM to an existing project, three key components need to be understood.
1. Planned Value (PV): Planned Value is the value of the authorised budget assigned to the work scheduled. In simpler terms, it is the budget assigned to the activities and the period within the scope of the analysis. The PV is always exclusive of any management reserve. It is also known as the Budgeted Cost of Work Scheduled (BCWS). The cumulative Planned Value is also known as Performance Measurement Baseline (PMB), therefore the PV for a completed project is the same as the Budget At Completion (BAC).
2. Earned Value (EV): Earned Value is the value associated with the actual work performed within the stipulated time frame. EVA uses PMB to calculate EV for the part of the project that has been completed so far. Additionally, for every element of the Work Breakdown Structure (WBS), EV can help measure the work performance. Therefore, EV helps you understand the current performance of your project and predict long-term trends within and beyond project performance. It is also called the Budgeted Cost of Work Performed (BCWP).
You May Also Like: A Complete Guide for Splunk Certification
3. Actual Cost (AC): Actual Cost refers to the real cost realised or incurred due to the work performed on a given day. It includes cost elements such as direct costs, indirect costs, working hours etc. All of these values can be derived from invoices, account books and other sale or purchase-related documents. AC is short for ACWP, which stands for Actual Cost of Work Performed. One thing to note is that while PV and EV are measured in a given range, the AC does not have an upper limit. As a project manager, you should try to keep your AC within the range determined within the EV and PV. It becomes a matter of concern if your AC exceeds both these figures.
Other common terms used while calculating earned value are
EVM helps project managers to measure project performance and understand variance and costs involved. The main benefits of EVM are:
The guidelines to be followed for EVM calculation can be broken down into five sections or phases.
This phase includes establishing the constraints of the project. One of the main responsibilities of the project manager during this phase is establishing a Work Breakdown Structure (WBS), defining the tasks to be performed and their relation with the pre-defined deliverables. You also need to define the Organisation Breakdown Structure (OBS) to identify who will be responsible for which task in which department, thus delegating and defining responsibilities within the WBS. Thus the organisation phase helps define what (WBS) needs to be done and who (OBS) needs to do it.
During this phase, the project manager needs to go over the basic requirements for planning the project in phases, scheduling deadlines for each phase, and allocating a budget to each phase of the project. The resources that you estimate at this phase are called the BCWS or Budgeted Cost of Work Scheduled. The total budget that is phased out and allocated to different parts of the project is also called the Performance Measurement Baseline or PMB, or Planned Value.
All projects start with a level of uncertainty. You can never be 100% sure of how your project execution will progress, so you need to have some room to accommodate slight delays, errors and feedback. For this reason, project managers also set aside additional funds known as a management reserve.
In this phase, you need to calculate the correct Actual Cost of Work Performed (ACWP). This should be in line with the way work is planned and budgeted. The AC must be captured at the appropriate time, aligned with the delivery or completion schedule of important products and/ or resources. A common practice is to collect the material costs in the same month the BCWP is collected to avoid ‘booking lag’, a very common source of misleading cost variance.
This phase needs intense attention to variation in costs and scheduling, documenting cause, impact and correction, and, if needed, calculating a new EAC (Estimate at Completion). The project manager and data analysts and strategists on the team go through the data collected through the project to identify root causes of variance, their impact on the current and future work effort and take corrective action. Project managers must carefully review cost and schedule variances during every reporting cycle, as they are essential while calculating EAC.
Additional Read: The Benefits of Obtaining an SAS Certification
The last phase emphasises the implementation of changes directed by the client, which sometimes includes orders to stop work (SWOs). It also includes implementation of project planning, analysis and implementation of changes internally. This phase is pretty much mandatory for proactive, meaningful EVM with a regularly changing baseline.
At any point during the project, you can calculate the EV and cross-check your accounts for data on the AC up to that point in the project. Also, calculate the PV that was budgeted for the same work.
Calculate the two variances - cost variance (CV = EV - AC) and schedule variance (SV = EV - PV). Check if the results you get are negative or positive. This should help you conclude how your project is going.
Next, calculate the Scheduled Performance Index (SPI = EV/AC) and Cost Performance Index (CPI = EV/AC). This should help you understand if there is a performance issue so far.
Based on the values that you can determine - SV, CV, SPI and CPI - you will see where your project is lacking and things that are not going as planned. This will help you to make decisions that can bring your project back on track.
ALSO READ: 6 Major Factors Affecting Project Management Success in your Organisation
You can also calculate project completion estimates based on the current progression of your project. This can be done by figuring out your Estimate at Completion or EAC. EAC = ETC + AC. ETC can be calculated based on the flow and patterns of your project at the time of completion.
At times, nothing that can be done to rescue the project and set it on its decided course. If you know there is no feasible way to save the project, it is best to close the project and inform all the stakeholders accordingly. If the project can still be rescued, recalculate and create a new estimated baseline and replace it with the original PMB.
Archer Charles has top education industry knowledge with 4 years of experience. Being a passionate blogger also does blogging on the technology niche.