Which of the following is delivered at the end of the Sprint?

Answer :
  • An increment of Done software

Product Backlog should be ordered on the basis of...

Answer :
  • Value of the items being delivered

Which of the following are the main responsibilities of a self-organizing development team?

Answer :
  • Develop the Sprint Backlog items

What does a Burn down chart display?

Answer :
  • Amount of remaining work with respect to time

A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is not a characteristic of this project if it is managed according to Scrum?

Answer :
  • Detailed upfront planning will be done to ensure that risks are identified early on

To enable the Product Owner to successfully deploy the product release as a part of the Ship Deliverables process, the Scrum Master should ensure that…

Answer :
  • The Scrum Team creates Deliverables as agreed upon

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following should they use to arrive at a conclusive decision?

Answer :
  • Gap Analysis

What happens when all the Sprint Items cannot be completed?

Answer :
  • The Sprint ends with the done items

What should a Development Team do FIRST during a Sprint Planning meeting when they have realized that they have selected more than the items they can complete in a Sprint?

Answer :
  • Inform the Product Owner

When is a Sprint Retrospective ceremony performed?

Answer :
  • At the end of each Sprint