Certified Software Quality Analyst CSQA Quiz Questions and Answers

Which of the following planning activities is associated with the quality planning question "where do we want to go"?

Answer :
  • Objectives and Goals Planning

The focus of post-implementation reviews or post mortems is to:

Answer :
  • Improve the process

Which one of the following is NOT one of the change control procedures?

Answer :
  • Developer should provide access rights for the change in configuration management tool.

The process of implementing a new or improved approach is called:

Answer :
  • Deployment Process

Which of the following is NOT an example of a key indicator?

Answer :
  • Estimated Size

The COSO Enterprise Risk Management model's ____________ component ensures that management has a process in place to set objectives and that the chosen objectives support and align with the organization's mission/vision.

Answer :
  • Objective Setting

A help desk employee is allowed to hire a courier to deliver a report needed quickly by a user; but only up to a cost of $100. This means that the employee is being ___________.

Answer :
  • Empowered

Stress-testing subjects a system to which of the following types of tests?

Answer :
  • Large Volumes of Transactions

Which of the following tools category has a mathematical focus and is related to data collection or interpretation?

Answer :
  • Statistical Tools

The system having adequate safeguards to protect the data against damage refers to which CSF?

Answer :
  • Security