PRINCE2® Agile Foundation Quiz Questions and Answers

Which describes a PRINCE2 principle? 

Answer :
  • It should be tailored to suit the project's size, capability and risk 

Which Scrum role is responsible for prioritizing items on the product backlog? 

Answer :
  • Product owner 

Which should be an objective of a retrospective?

Answer :
  • To identify Key process improvements to implement in the next sprint

According to PRINCE2 agile, which form of communication shows that a team is vibrant and interactive?

Answer :
  • Using visualization to display information

How does PRINCE2 Agile describe Scrum?

Answer :
  • Scrum is the most well-known agile framework

Where should team norms and values, such as the length of the team's stand-up meetings be included?

Answer :
  • In working agreements

When is it most suitable to run a workshop without a facilitator? 

Answer :
  • When the participants have established working norms 

What is not typically included in a user story? 

Answer :
  • The fully defined solution to deliver the requirement 

Which term is used to describe "the rate of progress a team is making "? 

Answer :
  • Velocity 

Which statement explains the target 'protect the level of quality for flexible delivery?

Answer :
  • It leads to a lower cost throughout the life of a product