PRINCE2® 6th Edition Foundation Quiz Questions and Answers

Answer :
  • Manage by exception

Explanation :

Permisiable Deviation
Answer :
  • Create user and supplier groups

Explanation :

Project Control
Answer :
  • A measurable improvement resulting from an outcome
Answer :
  • The area of uncertainty in terms of the threat or opportunity
Answer :
  • Managing a Stage Boundary
Answer :
  • A measure of the likelihood of the risk occurring
Answer :
  • Exploit
Answer :
  • An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
Answer :
  • Establish how the project will ensure that all products created meet their requirements
Answer :
  • Outcome