PRINCE2® 6th Edition Foundation Quiz Questions and Answers

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of the plan?

Answer :
  • Manage by exception

Explanation :

Permisiable Deviation

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Answer :
  • Create user and supplier groups

Explanation :

Project Control

Which describes a project benefit?

Answer :
  • A measurable improvement resulting from an outcome

Which describes a risk event?

Answer :
  • The area of uncertainty in terms of the threat or opportunity

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Answer :
  • Managing a Stage Boundary

Which describes risk probability?

Answer :
  • A measure of the likelihood of the risk occurring

Which risk response type is appropriate to respond to an opportunity?

Answer :
  • Exploit

Which statement defines a risk?

Answer :
  • An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

What is the purpose of the Quality theme?

Answer :
  • Establish how the project will ensure that all products created meet their requirements

What is the result of the change derived from using the project’s product?

Answer :
  • Outcome