Primavera P6 Professional Advanced Rel 19 Ed 1 Quiz Questions and Answers

What is Banana Curve?

Answer :
  • It refers to the cummulative curve

What is the purpose of Resource Usage Profile?

Answer :
  • To view resource or role allocations

Can we connect with a different database on Primavera?

Answer :
  • Yes

Where we can see resource overallocation?

Answer :
  • Resource Usage Profile

How many duration types we have in Primavera

Answer :
  • 4

How many % complete types do we have?

Answer :
  • 3

If Fixed Units is set , Units/Time is changed from 10 to 12, - how much will be the duration (10 days, 8H/D, 80 units initially)

Answer :
  • 7

If Fixed Units is set , Units/Time is changed from 10 to 14, - how much will be the duration (10 days, 8H/D, 80 units initially)

Answer :
  • 6

Planned Value Cost is --------

Answer :
  • How much work should have been done

Earned Value Cost is ---------

Answer :
  • How much work was actually done