Project creates ______based on assignment work and resource rates.
Answer :
budgets
Explanation :
As resources are assigned to tasks and assignment work estimated, the program calculates the cost, equal to the work times the rate, which rolls up to the task level and then to any summary task, and finally to the project level.
You are working on a project file that contains many linked subprojects. When saving the files, what option can you use to immediately save the open files, including those that have not changed?
Answer :
Yes to All
You can use the help of the task inspector to do what?