Certified Associate in Project Management (CAPM)® Certification Prep Quiz Questions and Answers

Answer :
  • Strong Matrix

Explanation :

Projectized Organization: Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project. Strong Matrix: The project manager is assigned full time and has a f
Answer :
  • Enterprise benefits measurement methods when selecting a project

Explanation :

Projects are seeded from the recognition of a regulatory or business need. Cost benefit analysis, scorecard modelling , payback periods, and internal rate of return are examples of benefits measurement methods when selecting a project. Best Option is A
Answer :
  • Arrow Diagramming Method (ADM)

Explanation :

The arrow diagramming method (ADM) is also referred to as activity-on-arrow (AOA) diagramming method. Precedence diagramming method (PDM) is also referred to as activity-on-node (AON) diagramming method
Answer :
  • Direct and Indirect

Explanation :

Make-or-buy decisions measure the costs of both options. When doing this analysis, it should include both direct and indirect costs so that the final decision is based on comparisons that are equal.
Answer :
  • A) Strategic planning determines which projects will be choosing in order to achieve the organizational goals
    B) Strategic planning determines which projects will be sponsor in order to achieve the organizational goals
    C) Strategic planning determines these are the projects that get chosen and funded
    All of the above

Explanation :

Strategic planning determines which projects will be choose or sponsor in order to achieve the organizational goals. Strategic planning determines these are the projects that get chosen and funded.
Answer :
  • A) Requirements document created in collect requirements process
    B) Project files from previous projects
    C) Project Charter
    All of the above

Explanation :

Define Scope - Inputs Requirements document created in collect requirements process, Project Charter and Organizational Process Assets (Project files from previous projects, lesson learned)
Answer :
  • Balanced matrix

Explanation :

Balanced matrix: Power is shared between both Functional and Project Manager. In this case you include the functional manager in the meeting therefore it is Balanced matrix organization.
Answer :
  • Parametric estimating

Explanation :

Parametric Estimating: Estimating the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate.
Answer :
  • During the initiation stage

Explanation :

output of Initiation process : Project charter PM assigned Constraints Assumptions Project manager is assigned to a project During the initiation stage.
Answer :
  • Estimating the cost of individual work items and then rolling up the costs to arrive at a project total

Explanation :

Bottom-up estimating: Estimating the cost of individual work items and then rolling up the costs to arrive at a project total. It is more accurate