During sprint execution, a Scrum team uses "information radiators" such as the task board or sometimes a sprint burn-down chart. Who are these for?

Answer :
  • The team, so they can take responsibility for their own work habits and track progress

In an organization that embraces Agile values, who would be responsible for tool selection and configuration?

Answer :
  • The teams, who would have to coordinate with each other

Which of the following ACTIVITIES ARE not timeboxed?

Answer :
  • Project Retrospective

When forming an Agile project team it is BEST to use:

Answer :
  • Generalized Specialists

When analyzing processes, what becomes increasingly significant for managers to understand in regards to individual skills?

Answer :
  • A group understanding of processes allows teams to execute their jobs more effectively and efficiently, hut it can never substitute skill

What Agile principle can help in chaotic situations?

Answer :
  • Incremental delivery

For one of your product, optimal cost of change (CoC. was estimated to be 100 story points but at the end of the iteration actual C0C was found to be 200 story points. What is the Technical debt that your project had encountered (if any)?

Answer :
  • 100 Story points

If a team can complete 10 story points In an iteration then how long will it take for the team to complete 100 story points?

Answer :
  • 10 Iterations

According to Agile manifesto what carries more value?

Answer :
  • Individuals and interactions over processes and tools.

There was an Issue In your project and your manager kept asking “why?’ several times. What is he doing?

Answer :
  • He Is executing collaboration.
  • He is executing “Five whys” a Lean tool.