55205-A: Mastering Microsoft Project 2016 Quiz Questions and Answers
You are a project manager who uses Project Standard 2013. You are creating a preliminary project schedule and are estimating the number of resources required before finalizing the schedule. You do not have named resources to complete the tasks, but you know the necessary resource roles. One of the roles needed is the architect. You need to estimate how many architect hours are required to complete the work. What should you do?
Answer :
Add a Work Resource named architect
You are a project manager who uses Project Professional 2013. After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the originally scheduled dates. You need a graphical view that shows the current schedule to baseline. Which view should you use?
Answer :
Tracking Gantt view
Which of the following is not a Resource Type in Microsoft Project 2013?
Answer :
Labor
We can create our own Ribbon Pannel.
Answer :
Yes
We can create our own Quick Access Toolbar.
Answer :
Yes
We can rename the Group Name of the Custom Q Access Toolbar.