PRINCE2® Agile Foundation and Practitioner Quiz Questions and Answers

In an organization that embraces Agile values, who would be responsible for tool selection and configuration?

Answer :
  • The teams, who would have to coordinate with each other

Which should be an objective of a retrospective?

Answer :
  • To identify Key process improvements to implement in the next sprint

Which product identifies the management stages and timescales of a project?

Answer :
  • Project Plan

Identify the missing words in the following sentence. The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

Answer :
  • Project support

Which of the following is delivered at the end of the Sprint?

Answer :
  • An increment of Done software

What happens when all the Sprint Items cannot be completed?

Answer :
  • The Sprint ends with the done items

What should a Development Team do FIRST during a Sprint Planning meeting when they have realized that they have selected more than the items they can complete in a Sprint?

Answer :
  • Inform the Product Owner

According to PRINCE2 agile, which form of communication shows that a team is vibrant and interactive?

Answer :
  • Using visualization to display information

Which is the base product against that the Project Board can assess progress, issues, and ongoing viability questions?

Answer :
  • Project Initiation Documentation

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Answer :
  • Quality