PRINCE2® 6th Edition Practitioner Quiz Questions and Answers

Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?

Answer :
  • Scope

Explanation :

What is to be deliver ?

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Answer :
  • Create user and supplier groups

Explanation :

Project Control

Which is a type of issue?

Answer :
  • A request for change

Explanation :

Ask for change

Which characteristic distinguishes a project from regular business operations?

Answer :
  • Introduces business change

Which is a benefit of using PRINCE2?

Answer :
  • Provides for the efficient and economic use of management time

Which is not one of the PRINCE2 integrated elements?

Answer :
  • The products

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Answer :
  • Quality

When should the Project Board refer to corporate or program management for a decision?

Answer :
  • It is forecast that project level tolerance will be exceeded

Which two roles are linked by the Managing Product Delivery process?

Answer :
  • Project Manager and Team Manager

Which role is responsible for creating Checkpoint Reports?

Answer :
  • Team Manager