Which of the following does the Executive need to ensure is in place before the project initiates?

Answer :
  • An understanding of how the project will contribute to corporate objectives

Why does PRINCE2 recommend three different levels of plans?

Answer :
  • To provide appropriate detail to each of the different levels of management within the project

Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?

Answer :
  • Scope

Which is a type of issue?

Answer :
  • A request for change

Which product identifies the management stages and timescales of a project?

Answer :
  • Project Plan

Which is the purpose of the change theme?

Answer :
  • To assess how possible changes will impact the baselined aspects of the project 

Which product documents the information needed to demonstrate continued business justification?

Answer :
  • Business Case

What takes place during the Closing a Project process?

Answer :
  • Ownership of the project's products is transferred to the customer

Which is the base product against that the Project Board can assess progress, issues, and ongoing viability questions?

Answer :
  • Project Initiation Documentation

Which aspect of project performance must be managed to ensure the project's products are fit for purpose?

Answer :
  • Quality